"Antonio works hard to achieve the functionality that schools demand, yet produces spaces that are very aesthetically pleasing."
Mona Chadwick
Superintendent, Hempstead ISD
The district needed additional classroom space at the Elementary level. Studies were done at both elementary schools in the district to decide upon the most cost effective way of adding classroom space. Our study showed that Pasemann Elementary provided an advantage because it would not require additional restrooms to accommodate the increased population. The addition includes 8 classrooms at the 2nd through 5th grade level.
Additional work was done at Pasemann to improve traffic flow and parent drop off and pick up.
Owner:
Taylor Independent School District
Addition Size:
8,250 square feet
Completion:
Winter 2017
Services Provided:
• Project begun at Fromberg Associates
• Construction Phase Services
Key Personnel:
Antonio Naylor, AIA, ALEP, Project Executive
Clifton Stuckey, AIA, Project Manager